| June 2008: |
Swiss Post’s Executive Management gives the green light for the construction of a 13-storey high-rise in northern Bern to accommodate the head office of PostFinance. |
| November 2008: |
Over 93% of voters in Bern approve the necessary zoning change. |
| June 2009: |
The jury announces the competition winner (IGOR project by “Büro B Architekten und Planer AG and Overhage & Roggo Architekten”). |
| August 2009: |
Project launch with the architects, general contractor HRS, Swiss Post Real Estate and PostFinance Logistics. |
| December 2009: |
General contractor HRS submits the planning application. |
| April 2010: |
Berne city council unanimously approves handover of the development site by the city under a ground lease. |